Chilled Water Valve Tags: CHWS/CHWR Labeling, Colors and Wording per ASME A13.1
Get this made: TagBuilder (Solid Ideas Engraving, Waterford, PA) engraves Design your own (from $2.99). No minimum order, no setup fees, most orders ship in 2–3 business days, rush available. Custom text and size: open this design in the configurator. Or email the spec to support@tagbuilder.net for a written quote and PDF proof the same business day.
You are standing in a mechanical room with forty identical valves on two loops, and the balancer needs to know which one is the AHU-3 return. A tag scheme decided before install saves that walk every time.
Disclaimer: general information, not legal or compliance advice. Codes change and inspectors interpret them differently, so confirm requirements with a qualified professional. Full disclaimer
Valve tags and pipe markers do different jobs
A pipe marker tells you what is inside the pipe and which way it flows. A valve tag tells you which specific valve you are holding and, usually, what it does. You need both on a chilled water loop, and they are not interchangeable.
ASME A13.1 is a standard for identifying piping systems. It covers the content of the marker, the color scheme, letter size and placement. Valve tags are generally driven by the project specification and the valve schedule rather than by A13.1 itself. For the marker side, see the pipe marking requirements guide.
How A13.1 treats chilled water
Chilled water is not a hazardous fluid in the A13.1 sense. It falls in the group of water services (potable, cooling, boiler feed and other water), and the commonly used scheme for that group is green background with white lettering. That is why most chilled water markers and tags you see are green and white.
Two cautions before you order:
- Confirm the project spec. Some specs call out a different color for chilled water, or a color per system. The spec governs the job.
- Check the edition and the AHJ. Color tables and sizing rules are revised between editions, and some owners add their own standards on top.
If the spec is silent, green and white is a reasonable default, but get the engineer to confirm it in writing before you buy a few hundred tags.
What Section 23 05 53 usually asks for
Division 23 identification sections, commonly Section 23 05 53, typically ask for a tag on every valve except those at fixtures and plumbing trim. They also usually ask for a valve schedule that lists each tag number, location, service, function and normal position. The legend is commonly CHWS for chilled water supply and CHWR for chilled water return, sometimes spelled out on a second line.
Wording, tag size, fastener type and schedule format all vary by spec, so read your project's version. The Section 23 05 53 guide covers the spec language and schedule format in detail, so this article sticks to the chilled water specifics.
A numbering pattern that holds up
A good tag number is readable from three feet away and sortable in a spreadsheet. A pattern that works on chilled water plants is:
SYSTEM-EQUIPMENT-SIDE-FUNCTION
- SYSTEM: CHW for chilled water.
- EQUIPMENT: the equipment the valve serves, such as CH1, CHWP2 or AHU3.
- SIDE: SUP for supply, RET for return.
- FUNCTION: ISO, BAL, DRN, VNT, CHK or BYP.
Keep the same pattern across the whole job. If the drawings say AHU-3 and the tag says AHU03, someone will eventually ask whether they are the same unit.
Valve function, abbreviation, size and legend
The table below is a starting point. Sizes are typical for round or rectangular tags read at arm's length; adjust to your spec and to how much room you have on the stem extension or handle.
| Valve function | Abbreviation | Typical tag size | Suggested legend (line 1 / line 2) |
|---|---|---|---|
| Isolation | ISO | 1.5 in round or 2 x 1 in | CHW-AHU3-SUP-ISO / CHWS ISOLATION |
| Balancing | BAL | 1.5 in round or 2 x 1 in | CHW-AHU3-RET-BAL / CHWR BALANCING |
| Drain | DRN | 1.5 in round | CHW-AHU3-DRN / CHW DRAIN |
| Vent | VNT | 1.5 in round | CHW-AHU3-VNT / CHW AIR VENT |
| Check | CHK | 2 x 1 in | CHW-CHWP2-CHK / PUMP 2 DISCHARGE CHECK |
| Bypass | BYP | 2 x 1 in | CHW-CH1-BYP / CHILLER 1 BYPASS |
Check valves have no handle to turn, but they still go in the schedule, and a tag helps the next person understand the flow path.
Worked example: two chillers, three pumps, six coils
Take a small plant with chillers CH-1 and CH-2, primary pumps CHWP-1, CHWP-2 and CHWP-3, and six AHU cooling coils. Each coil gets a supply isolation valve, a return balancing valve, and a drain and vent at the high and low points.
Here is how AHU-3 reads in the field:
- CHW-AHU3-SUP-ISO on line 1, CHWS ISOLATION on line 2.
- CHW-AHU3-RET-BAL on line 1, CHWR BALANCING on line 2.
- CHW-AHU3-DRN on line 1, CHW DRAIN on line 2.
- CHW-AHU3-VNT on line 1, CHW AIR VENT on line 2.
Pumps and chillers follow the same pattern:
- CHW-CH1-SUP-ISO / CHILLER 1 SUPPLY ISOLATION
- CHW-CH2-RET-ISO / CHILLER 2 RETURN ISOLATION
- CHW-CHWP2-SUC-ISO / PUMP 2 SUCTION ISOLATION
- CHW-CHWP2-CHK / PUMP 2 DISCHARGE CHECK
For this plant that is roughly six coils at four valves each, plus the chiller and pump valves, so a few dozen tags. The matching schedule has one row per tag number: location, service, function, normal position (open, closed, throttled) and the drawing sheet. The line 1 number on the tag must be identical to the number in that row, character for character.
Fasteners on insulated, sweating pipe
Chilled water pipe runs below the dew point of the room, so it is insulated with a vapor barrier. That barrier is what keeps the insulation dry. Every hole you put through it is a place for condensation to get in.
- Do not screw or rivet a tag into the insulation jacket.
- Hang the tag on a stem extension, handle or yoke that stands outside the insulation, using a chain or a cable tie suited to the temperature and environment.
- Use a chain length that lets the tag hang readable without dragging on the insulation or being caught by the handle swing.
- For valves with no usable handle, consider a tag on a short bracket fastened to the hanger or support, and note that in the schedule.
Engraved two-ply plastic tags handle condensation well because the lettering is cut into the surface rather than printed on it. Where a spec calls for metal, engraved stainless is the usual alternative.
Keeping tags, schedule and drawings in agreement
Most tag problems are not fabrication problems. They are coordination problems. Before you place the order:
- Pull the valve schedule and the latest drawings, and confirm the numbering.
- Check for valves added by addenda or field changes.
- Decide whether line 2 is a function or a service name, and apply the choice to every tag.
- Order a few spares for the valves that always get added at commissioning.
If the engineer revises the numbering after the tags are made, redo the schedule and the tags together rather than patching one.
Frequently Asked Questions
Is chilled water always green and white?
Green with white lettering is the common scheme for cooling and other non-flammable water under A13.1, and many specs adopt it. Some projects specify something different, so confirm the color in the project spec and check the current edition of the standard.
Should I use CHWS and CHWR or spell it out?
Many specs call for CHWS and CHWR as the legend, and some add a second line with the full words. Use what the spec says. If it says nothing, the abbreviations with a plain-language second line are easy for new maintenance staff to read.
Do valve tags replace pipe markers?
No. Pipe markers identify contents and direction along the pipe. Valve tags identify one specific valve. A project normally needs both, and the spec will say where each one goes.
What size should chilled water valve tags be?
A 1.5 inch round or a 2 x 1 inch rectangle is common for valve tags and gives room for a two-line legend. The right size depends on the spec, the viewing distance and the space on the valve.
How do I attach a tag to a valve on insulated pipe?
Hang it from a stem extension, handle or yoke outside the insulation, with a chain or a cable tie. Avoid fastening through the insulation jacket, because that breaks the vapor barrier and can lead to sweating and wet insulation.
Can I put the tag number on the tag and the service on the pipe marker?
Often yes, and many jobs do exactly that. Whether the service wording must also appear on the tag is a spec question, so check before assuming.
Order chilled water valve tags engraved with your CHWS/CHWR numbers and valve schedule.
If you are tagging a plant from scratch, start with the valve tag shop for the tags, and use the pipe markers for the lines themselves. For chillers, pumps and towers, the cooling tower and chiller equipment labels guide covers the nameplates that go with them.
Disclaimer. This article is provided for general informational purposes only and does not constitute legal, safety, or professional compliance advice. Regulations, standards, and codes are subject to change and may be interpreted differently by authorities having jurisdiction (AHJ). Always consult with qualified safety professionals, licensed engineers, or legal counsel to determine the specific requirements applicable to your facility. TagBuilder is not responsible for any actions taken based on this information.
UL, NFPA, NEC, ASME, CEMA, TIA, ANSI and OSHA are names or marks of their respective organizations; TagBuilder is not affiliated with or endorsed by any of them. Requirements above are paraphrased summaries, not the text of any standard. Always work from the current published edition and your AHJ.